Terminal shutdown exposed limited fuel reserves
The Water and Power Authority's November 24 account linked the outages to a propane shutdown that increased the plant's dependence on diesel. At contractor Saintnals' request, the terminal was shut down around 3 a.m. Monday for critical repairs. Diesel stocks were already low, and rising evening electricity demand added to the strain.
WAPA said the financial pressures behind its limited fuel reserves had been building for months. "Financial constraints and ongoing under-recovery have limited the Authority's ability to build and maintain the fuel inventory levels needed to provide a greater cushion against unexpected disruptions," the release stated.
The utility said it had arranged to obtain diesel from local vendors as quickly as possible. It provided neither an inventory figure nor details about purchase volumes or delivery dates.
This was the second propane-supply disruption reported on St. Croix that month. According to WAPA, operational problems at the Saintnals-run LPG terminal interrupted propane supplies and caused outages on November 18. Generators used diesel in the interim, with service restored November 19.
Tuesday's interruptions and late-night restoration
Some feeders began experiencing lengthy interruptions around 8:30 a.m. Tuesday as plant staff rationed the available diesel to avoid wider outages, WAPA said. Support from the island's three solar farms helped the utility preserve service to critical feeders. Some areas consequently retained power earlier in the day while others endured extended interruptions.
Early alerts put the expected completion of terminal repairs at about 3 p.m. WAPA anticipated three-hour outage rotations between 4 p.m. and 11 p.m.; by 5:30 p.m., it had announced those rotations without confirming that propane service had resumed.
A subsequent release set Saintnals' expected return-to-service time at approximately 8 p.m. Tuesday. That remained a target, not a report that repairs were complete.
Later that evening, WAPA announced that Saintnals had finished the work and said restoration for affected customers was expected to begin in roughly two hours while the system repressurized. The utility then confirmed that every St. Croix feeder had been restored by 11:48 p.m., according to updates recorded by VI Land Guide's WAPA outage tracker.
Generator failures in St. Thomas–St. John
The St. Thomas–St. John district was dealing with a separate generation problem. WAPA reported taking another unit out of service Monday night for urgent repairs, but did not name it or estimate when it would return. As consumption rose Tuesday, the utility revised its rotation schedule several times.
At a Senate committee hearing, CEO Karl Knight attributed the district's ongoing blackouts to generator failures, not fuel shortages, The Virgin Islands Daily News reported.
Knight said work on Wärtsilä Engine 5 at the Randolph E. Harley Power Plant began November 21. He expected completion of those repairs to provide enough generating capacity to end the prolonged outages, according to the Legislature of the U.S. Virgin Islands.
His near-term plans for the district also included two 2.5 MW Cummins generators at the Harley plant, providing a combined 5 MW and black-start capability; repairs to the 18 MW Unit 15 and 30 MW Unit 23; and connection of at least 10 MW of solar generation at Estate Fortuna.
Knight also outlined a proposed six-month lease for a power ship supplying at least 30 MW at Krum Bay. The proposal, which applies to the St. Thomas–St. John system, calls for $2.85 million upfront in addition to electricity charges. Funding was still under discussion.
Standby generation and longer-term additions
The district's plans also call for 10 MW of standby generation on St. John. Four Cummins generator sets, each rated at 2.5 MW, arrived in the territory on August 26, 2026. Together, they represent an $8 million investment, according to the USVI Office of Disaster Recovery.
WAPA said the generators had completed load testing in May 2026 and the necessary air permits had been obtained. Contractor RG Engineering projected completion of installation, commissioning and startup by January 2027.
For St. Croix, Knight described plans to add 30 MW at Richmond by installing three refurbished Solar Turbine Mars 100 units by June 2027. His longer-term program calls for new generating equipment at both Richmond and Harley by August 2030.
Billing questions and emergency board agenda
The outages have also left billing issues unresolved. Knight acknowledged that estimated bills might not account for the reduction in electricity use during interruptions. He said customers' accounts would receive credits, without specifying when or how the adjustments would be calculated.
WAPA scheduled an emergency board meeting on Microsoft Teams for 9 a.m. Wednesday, November 25. The public portion of the agenda covers conditions on St. Croix and St. Thomas, with an executive session afterward for legal and personnel matters.