Production scheduled from late 2026
The contract will provide work for Nexans' impregnated paper-insulated cable production lines from late 2026 to mid-2028. It covers a 110 kV mass-impregnated (MI) cable system that the company describes as essential to the HVDC link's safe, reliable operation.
Nexans signed the subcontract with Hellenic Cables within the consortium formed with Asso.subsea. Greek grid operator IPTO awarded the overall project to Hellenic Cables through its wholly owned subsidiary Fulgor S.A.
The order comes to a company operating in 39 countries with 12,830 employees. According to its corporate profile, Nexans generated €6.1 billion in standard sales in 2025.
A larger connection to the Dodecanese
The Nexans supply is part of a 1 GW, 320 kV high-voltage direct-current interconnection linking the Dodecanese islands with Greece's mainland transmission system. The full link includes about 1,260 km of submarine cable and 30 km of underground cable. Nexans describes its scale as among the most ambitious power transmission projects in the Mediterranean.
According to Cenergy Holdings, the turnkey contract covers engineering, procurement, construction and installation and is worth approximately €1.5 billion. Powergame.gr reports the value as €1.48 billion. Work is expected to begin in the fourth quarter of 2026, with completion scheduled for 2030.
Cenergy Holdings says the connection will allow oil-fired power stations on the islands to be retired gradually. It describes those plants as costly and carbon-intensive and says the new link will substantially improve electricity supply security and reliability.
Powergame.gr identifies the cable contract as the largest individual package in the wider Dodecanese electrical interconnection project, whose total budget is €2.957 billion. A separate tender, budgeted at €809.1 million, covers two converter stations.
One station is planned for the Korfos area of Corinthia, near the new Corinth Ultra High Voltage Center; the other is planned for Mastichari on Kos. Both are to use Voltage Source Converter technology similar to the system used for the Crete-Attica interconnection.
Shares recover some ground after recent losses
Ideal Investisseur attributes the stock's advance to the company-specific contract news. The broader session was marked by technology-stock selling on Wall Street and subsequently in Asia.
Despite the day's gain, Nexans shares were down 7.79% over 30 days and 4.13% over the week. At €123.10, the stock had returned to around its 20-day moving average of €122.54, but remained below its 50-day average of €130.63 and its 200-day average of €136.47. The gap to the latter was 9.8%.
Ideal Investisseur reports a neutral relative strength index reading of 48, which it says leaves open either a further rebound or renewed declines. It places support at €113.60 and resistance at €135.60.
Nexans reaffirmed its annual targets when it released nine-month 2026 results on October 22. It targeted EBITDA of around €805 million for the following year while signaling a normalization in PWR-Transmission activity. The donor's third-quarter figures show revenue of €2.585 billion and revenue growth of 44.9%.
This article is for informational purposes and does not constitute investment advice or a recommendation to buy or sell securities. Stock market investments can result in capital losses.