New routes and departure times
Line 256 will take a different route between Engrie-la-Ben station and the Saint-Denis University stop. The change is intended to make service more regular and transfers at Engrie-la-Ben easier. It will also alter access to the Camille Saint-Saëns Lyceum, Émile du Chale College and Jean-Bouin Sports Center.
The reorganization includes later-service adjustments for line 256. According to local news outlet actu.fr, its last departures will be at 12:40 a.m. Monday through Friday, 1:35 a.m. Saturday and 12:35 a.m. Sunday.
The revised line 337, between Mortefontaine market and Pierrefitte-Sten station, is intended to improve connections at transfer hubs. Its final weekday departure will move to 10:40 p.m. to align with the RER D train schedule.
The new line 357 will serve Mortefontaine market and Deuil-Montmagny station, taking over part of line 337's former route. It will provide a replacement link between central Deuil-la-Barre and Engrie-la-Ben, with buses every 20 minutes from 7 a.m. to 9 p.m., Monday through Saturday.
Safety concerns and project funding
Safety is the reason for removing Pn4: the crossing has recorded 70 accidents over the past 15 years, including four fatal accidents.
SNCF Réseau separately reports about 50 incidents since 2011, including broken barriers and collisions. The rail infrastructure operator says roughly 7,000 vehicles and two bus lines use the crossing daily. Each incident disrupts line H and TER Paris-Persan-Beaumont-Beauvais services for at least three hours, according to SNCF Réseau.
Removing the crossing and rebuilding the nearby road and rail infrastructure is expected to cost about 50 million euros. The Val-d'Oise department has allocated more than 20 million euros toward that total.
The project received a declaration of public utility from the Val-d'Oise prefect on June 27, 2022. That decision followed an early-2017 public consultation and a public inquiry held from December 10, 2021, to January 19, 2022.
Replacement crossings and work through 2027
The Pn4 closure marks the start of the third and final phase of a project running from October 2024 through 2027. Its first phase involved building a rail bridge in the Plante des Champs area, south of the Camille Saint-Saëns Lyceum. According to the town of Deuil-la-Barre, that phase officially ended on January 30, 2026.
The prefabricated bridge weighs 1,850 metric tons and sits south of Pn4. SNCF Réseau says it will provide a way for motorists, buses and emergency vehicles to cross the railway. A separate, existing rail-bridge crossing will be closed to cars and reserved for pedestrians and cyclists.
The second phase, scheduled from early 2026 through December 2026, covers road redevelopment and new roads between Pn4 and the new rail bridge.
The final phase will create an underground passage at the former Pn4 site for pedestrians and cyclists. The town's schedule places this phase in 2027, with construction by SNCF Réseau running from December 2026 to September 2027 after the crossing closes. SNCF Réseau says the passage will include stairs and ramps accessible to people with reduced mobility.