Google describes site searches as exploratory
French grid operator RTE has outlined a €67 million connection project in response to the Villedieu-sur-Indre request, Mediapart reported. Completing the connection could take seven to eight years.
Mayor Xavier Elbaz confirmed that he had discussed the site with Google. He said, however, that the company had told him it was putting those plans on hold to concentrate on its other local data center proposal. According to Elbaz, the property's current owner had also previously opposed selling to Google.
Mediapart reported that Google had contacted several municipalities across the Indre department in recent months, seeking a location for a "mirror data center" to accompany the Ozans Business Park project southeast of Châteauroux.
Google disputed the characterization of the sites as parallel projects. A spokesperson told DCD: "Google continuously explores land and grid opportunities to anticipate future infrastructure needs across the region. No final decision has been made on Ozans, or any other site, which are strictly part of ongoing, exploratory long-term planning rather than active parallel projects."
What Google has outlined for Ozans
The Ozans proposal is already in public consultation. Earlier this year, DCD reported that Google was set to pay €58.5 million ($68 million) for the 195-acre property. That reporting described capacity of up to 500 MW, with some reports suggesting an expansion to 1.1 GW. If built, it would be Google's first self-built data center in France.
Google France's consultation dossier provides a more detailed development plan, according to DC Market Insights. It puts the investment at about $10 billion, or €8.6 billion before tax, for six to eight buildings and Google's share of the grid connection. IT hardware and software are excluded. Alphabet would finance the project entirely from its own funds, without public subsidies.
The first building would cover about 30,000 square meters. Phase 1 calls for a 120 MW connection at 225 kV, followed by a 300 MW connection at 400 kV. The latter could reach 1,200 MW after RTE builds the planned Éguzon–Marmagne line.
According to Next, Ozans was one of 55 shovel-ready sites the French government identified in 2024 under the France 2030 plan as most suitable for large-scale data center development.
Consultation and local objections
The Commission Nationale du Débat Public (CNDP) is overseeing the preliminary public consultation on both the Ozans campus and its RTE connection. The process began on November 2, 2026, and is scheduled to end on January 10, 2027. Its first public meetings took place on November 9 and 13.
The proposal has drawn organized opposition. In mid-September 2026, Étrechet's mayor and several other municipal officials resigned in protest. The citizens' group "Ozans dire non" gathered close to 16,000 signatures on a petition seeking the project's abandonment. Les Énergies Renouvelables reported that opponents' concerns include water use, electricity demand and effects on the landscape.
Power infrastructure and the Engie agreement
For Ozans, the dossier gives a provisional grid connection cost of about €125 million: €25 million for the 225 kV link and €100 million for the 400 kV link. Google would cover 70% of the main supply connection and RTE the remaining 30%. Google would bear the entire cost of the redundant supply and private 400 kV substation.
Reaching the full 1,200 MW would require RTE's new Éguzon–Marmagne 400 kV line. According to Les Énergies Renouvelables and DC Market Insights, that line would extend about 100 kilometers, cost roughly €300 million and enter service no earlier than 2032. Work in 2021–22 increased the corridor's transmission capacity from 1,400 MW to 2,200 MW; the new line would raise it to about 7,600 MW.
Google also signed a memorandum of understanding with Engie on November 13, 2026. Subject to further agreements, Engie could become the Châteauroux project's preferred energy supplier and management partner. The memorandum is not a power purchase agreement, and its announcement specifies no capacity, price or contract duration, according to DC Market Insights.
The proposed cooperation covers a large-scale clean energy portfolio using multiple technologies, including renewable generation in France and both utility-scale and behind-the-meter batteries. It also encompasses energy efficiency for local homes, electric mobility and an assessment of recovering waste heat to supply district heating free of charge.
Engie will contribute technical and energy expertise to feasibility discussions and the public consultation under the CNDP framework.
France's wider data center demand
The Indre department is in Centre-Val de Loire, south of Paris, France's main data center market. Google currently operates no self-built data centers in the country. It uses infrastructure from companies including Equinix, Digital Realty and Global Switch, and offers a sovereign cloud through its partnership with French IT company Thales.
RTE figures cited by Citoyen put annual French data center electricity consumption at about 10 TWh, roughly 2% of national consumption, across about 300 sites. Eight sites connect directly to RTE's transmission network, with a combined capacity of 0.8 GW.
By May 2026, RTE had reserved nearly 18 GW for about 80 data center projects, compared with about 5 GW for some 40 projects at the end of 2024. The same figures show that facilities connected during the preceding two to three years were using, on average, only about 20% of the capacity they had requested.